PMP考試每天一練-2020年P(guān)MP考試練習(xí)題153
PMP考試練習(xí)題一: During user acceptance testing for the project deliverables, the customers finds one key function was not identified.What should the project manager review next with the customer? A. Responsibility assignment matrix B. Project scope statement C. Quality management plan D. Requirements traceability matrices 在用戶對項目可交付成果開展驗收測試時,客戶發(fā)現(xiàn)其中一個關(guān)鍵功能未被識別。項目經(jīng)理下一步應(yīng)該與客戶審查哪一項? A. 職責(zé)分配矩陣 B. 項目范圍說明書 C. 質(zhì)量管理計劃 D. 需求追溯矩陣 PMP考試答案解析:功能沒有識別出來,PM要和客戶查看需求追溯矩陣,看看客戶到底有沒有提過這個需求。 PMP考試參考答案:D PMP考試練習(xí)題二 After indentifying a risk that will negatively impact a project, the project team contracts an insurance company to manage the risk effects, Which of the following risk strategies was used? A. Avoid B. Transfer C. Mitigate D. Share 識別到一個將對項目產(chǎn)生負面影響的風(fēng)險后,項目團隊在一家保險公司投保來管理風(fēng)險影響。這使用的是下列哪一項風(fēng)險策略? A.回避 B.轉(zhuǎn)移 C.減輕 D.分享 PMP考試答案解析:買保險屬于風(fēng)險轉(zhuǎn)移。 PMP考試參考答案:B |